8/23/2011

BCS2413SAD Chapter 3 Exercise

Name _________________________ Date ___________

Chapter 3 – True/False

Instructions: Circle T if the statement is true or F if the statement is false.

T

F

1. A 2006 report published by The Standish Group concluded that 35% of software development projects were successful.

T

F

2. The project leader handles administrative responsibilities for the development team.

T

F

3. A task is any work that has a beginning and an end and uses company resources.

T

F

4. The project manager makes three time estimates for a task: worst-case estimate, best-case estimate, and weighted estimate.

T

F

5. CPM was developed by private industry.

T

F

6. A slack path is a series of tasks which, if delayed, would affect the final completion date of the project.

T

F

7. When transforming a task list into a PERT/CMP chart, the first step is to enter start and finish times.

T

F

8. A milestone is an event that could affect the project negatively.

T

F

9. A quantitative risk analysis includes the time and dollar cost to the company.

T

F

10. The first step in project management is to identify all the tasks, task duration, and task dependencies.